Practical advice on kitchen installation

You need to analyze this topic from the very beginning. And the beginning of the installation is in the assembly shop. And the first rule that any furniture maker should adhere to is to do everything that can be done before installation.

At the installation itself, doing those operations that could be done in the assembly shop is many times more complicated, for one simple reason – the room in which the set is installed is simply not suitable for furniture assembly.

There are no comfortable tables or workbenches, often there is no good lighting, and there is a time limit. That is, everything needs to be done on weight and quickly. In order to not waste time on the installation of what could have been done before, remember the above rule.

Before the “export” of the kitchen boxes must be collected, they should be installed facades, and these boxes, along with the facades, should be packed in a shipping film.By the way, about the transfer film: this is a very useful thing. Not only does it tightly fix the facades on the boxes, it still protects these facades and handles attached to them, from mechanical damage such as bumps, scratches and so on.

Therefore, on the packaging film it is not necessary to save (one roll of such a film can be enough to transport three kitchen sets, so it pays off “with interest”).Previously, in the assembly shop it is necessary to cut the hood into the appropriate box (if it is, of course, not a dome).

Also, do not forget to “dock” all the boxes of the kitchen set (make holes in the tightening bolts, which will pull them together). Very often, this is forgotten, and on the installation, this is lost a lot of time.

Before the modern kitchen cabinet set is delivered to the place, the room to which it is to be installed must be cleaned of all excess, since it requires as much space as possible for its installation.

Steps to install the cabinet

First set the lower base. Then, after it is installed the upper base

The lower base is set as follows:

First, all the lower boxes are installed, and they are joined together by tightening bolts. After that, the entire construction is exposed “on the level”.

The worktop is removed from the lower modules and a sink cuts into it (preferably immediately, while the worktop is still fixed on the boxes), a mixer is installed, and an opening for the hob is cut out.

After all this, the table top is installed on the lower modules, and rigidly fixed with self-tapping screws, and the hob is mounted in it.